Billingham, UK
As part of an overall risk analysis programme (Layers of Protection Analysis - LOPA) Johnson Matthey identified a high potential issue in relation to pipework that was routed internally within their O2 building which was carrying a mixture of chemicals.
As part of an integrated solution Hydrasun designed and built a new control panel within our own facilities and then project managed the installation of this together with the re-routing of existing and installation of new pipework on-site.